Public Notice on the Draft‑for‑Comments Version 100,000‑ton/year Green Intelligent Manufacturing Steel Cord Project of Shandong Daye Co., Ltd.
  2026-04-01  times

1. Basic Project Information

Project Owner: Shandong Daye Co., Ltd. Project Name: 100,000‑ton/year Green Intelligent Manufacturing Steel Cord Project of Shandong Daye Co., Ltd. Project Nature: New construction Project Location: No. 2 Xin South Street, south of Zhu‑Zhu Road, Xinxing Town, Zhucheng City, Weifang City, Shandong Province.

Project Content: The total project investment is RMB 900 million, of which RMB 21.39 million is allocated for environmental protection. Based on the existing southern plant premises, the project expands eastward on newly‑acquired land. It covers a total land area of 263 mu, with a total construction area of 122,610 m². A total of 2,075 sets of equipment including wet‑drawing machines, wire‑butt welding machines and electroplating lines will be procured for steel‑cord production.

The project will be implemented in two phases. Phase I requires an investment of RMB 450 million and will deliver an annual production capacity of 50,000 tons of radial‑tire steel cord upon completion. Phase II also requires an investment of RMB 450 million and will achieve an additional annual capacity of 50,000 tons of radial‑tire steel cord.

2. Name and Contact Information of the Project Owner

Project Owner: Shandong Daye Co., Ltd. Contact Person: Dou Xiaoxue Tel: 13953622640 E‑mail: sddyhbk2014@163.com

3. EIA Institution

EIA Compilation Institution: Weifang Environmental Science Research & Design Institute Co., Ltd.

4. Draft‑for‑Comments EIA Report and Public Comment Form

Download link for the full draft‑for‑comments report and public‑comment form: Link: https://pan.baidu.com/s/11jv‑zlznGApZCoki7os4lQ Extraction code: 53gv

Paper copies of the EIA report are available for review at the Office of Shandong Daye Co., Ltd. For access, please contact Dou Xiaoxue at Tel: 13953622640.

5. Methods and Channels for the Public to Submit Comments

This public notice shall remain open for 10 working days from its release date. Within this period, members of the public may fill in the public‑comment form and send it by e‑mail or other means to submit opinions and suggestions concerning the project and the environmental‑impact‑assessment work.

Shandong Daye Co., Ltd. April 1, 2026